after the U.S. government ordered Vineyard Wind to suspend operations after parts of a damaged turbine blade washed up on ...
The same Vineyard Wind offshore wind turbine that ... one executive order upon taking office that temporarily suspended ...
After the Trump administration suspended the Empire Wind offshore ... Management to rescind the construction and operations plan for Vineyard Wind 1. The revised plan was approved Jan. 17, 2025 ...
From the pier, it’s a short walk to the Vineyard Wind operations building, which houses a control center for the wind farm, locker rooms and warehouse space for parts. Special zoning to protect ...
Massachusetts has three offshore wind projects in various stages of development, include Vineyard Wind ... The Trump administration has also suspended federal funding for floating offshore ...
The 62-turbine wind farm is under construction 15 miles off the coast of Nantucket and Martha’s Vineyard and is expected to be completed this year. Vineyard Wind’s joint developers Avangrid ...
When Interior’s Bureau of Ocean Energy Management (BOEM) in January 2025 granted Vineyard Wind’s Revised Construction and Operations Plan (COP), it failed to consider or discuss the threat of ...
Despite the challenges, GE Vernova’s two remaining offshore wind projects have moved forward. The company had commissioned 17 units across Vineyard Wind in Massachusetts and Dogger Bank in the ...
The U.S. Supreme Court has declined to hear two cases challenging the federal approval of Vineyard Wind. The court denied the petitions Monday. Commercial fishing interests sued the federal ...
“Vineyard Wind 1, subject to the same highly expedited process, is replete with analytic deficiencies,” the group claimed, adding it “Respectfully requests the reopening, reanalysis, and revocation of ...